Repossession – Phase 5 and Final Stage of Redevelopment
The Repossession Phase marks the culmination of the Redevelopment Project, bringing the entire journey full circle — from vision to completion. It is a highly emotional and significant milestone for the Society and its members, as they finally return to their new, upgraded homes after years of anticipation and transition.
This phase begins once the construction of the new building is completed in all respects, and the Developer has secured the Full Occupancy Certificate (OC) from the relevant municipal authority. It concludes when all eligible members have taken formal possession of their new units within the stipulated notice period.
The total duration for this phase is generally around one month, and it is divided into the following two distinct stages:
Stage 1: Defect Rectification & Member Repossession
Active Agencies: Developer, Project Management Consultant (PMC), Managing Committee (MC)
SGBM Required: 1 (To initiate and approve the Repossession process)
Key Milestones:
Rectification of Snag Issues in individual flats (as reported by members)
Rectification and final finishing of external areas and common amenities (clubhouse, lifts, lobby, parking, etc.)
Formal Handover of newly constructed units to existing members
Member-wise walkthrough and joint verification with site engineers and PMC
Mock fire drill / safety demo (optional) for member awareness
Project Records to be Maintained:
Carpet Area Certificates of the new flats
Member-submitted Snag Lists and rectification reports
Final Parking Allotment Register
Virtual Completion Certificate from Developer or Architect
Members’ Possession Letters and Acknowledgement Receipts